*04/24/15 UPDATE*
Streetscapes West – Work planned for next week April 26th thru May 1st:
Weather permitting, final paving is scheduled to begin next Tuesday April 28th for the parking lot at the corner of 1st Street and Peoria Avenue and in Commercial Alley. The parking lot will be closed on Tuesday April 28th and Wednesday April 29thand will reopen for use Thursday after the completion of paving operations. To help offset the temporary loss of lot parking spaces, the Telegraph lot off of Highland is available for public parking.
*04/29/15 UPDATE*
Corrective work is planned for the intersection at 1st and Peoria beginning next week.
Streetscapes West – Work planned for next week May 3rd thru May 9th:
The contractor will begin replacing the defective pavement on the 1st Street and Peoria Avenue intersection on Monday. The approach blocks on the east, west and south sides of the intersection will be closed to through traffic but access and parking for local residents and businesses will be maintained within these blocks. The current plan is to complete the replacement next week and opening the following week once the pavement concrete reaches strength.
The Peoria Avenue Bridge shall remain open for southbound traffic detoured through Commercial Alley during these closures.